JKPDC

Name of Power House Configuration Installed Capacity in MW
STATE SECTOR
Jhelum River Basin
Lower Jhelum 3 x 35 105
Upper Sindh-I 2×11.3 22.6
Ganderbal 2×3+2×4.5 15
Upper Sindh-II 3×35 105
Pahalgam 3 x 1.5 4.5
Karnah 2×1 2
Chenab Basin
Chenani-I 5×4.66 23.30
Chennai-II 2×1 2
Chenani-III 3×2.5 7.50
Bhaderwah 3 x 0.5 1.5
Baglihar 3×150 450
Ravi Basin
Sewa-III 3×3 9
Indus Basin
Iqbal 3×1.25 3.75
Hunder 2×0.20 0.40
Sumoor 2×0.05 0.10
Igo-Mercellong 2×1.50 3
Haftal 2×0.50 1
Marpachoo 3×0.25 0.75
Bazgo 2×0.15 0.30
Stakna 2×2 4
                    Total                                                              758.70
CENTRAL SECTOR
Salal HEP 6×115 690
Uri -I 4×120 480
Dul-Hasti 3×130 390
Total 1560

JKSERC

    

Order’s No

 

LAWS , REGULATIONS AND NOTIFICATIONS (JKSERC) Year’s
Conduct of Business-Regulation 2005
Terms and Condition for Determination of Distribution Tariff-Regulation 2005
Appointment  of Consultant-Regulation 2005
Power Purchase of Procurement-Regulation 2005
Terms and Condition for Determination of Hydro Generation Tariff-Regulation 2005
Terms and Condition for Determination of Hydro Generation Tariff, Part II-B 2005
Open Access in Intra-State Transmission and Distribution-Regulation 2006
Terms and Condition for Determination of Hydro Generation Tariff, Part I-B 2006
Distribution Performance Standards-Regulation 2006
Open Access in Intra-State Transmission and Distribution 2007
J&K SERC Electricity Grid Code Regulation 2007
Security Deposit, Part I-B 2008
Open Access in Intra State Transmission and Distribution-Regulation, Part II-B 2008
Consolidated Amendment 2008
Electricity Ombudsman 2010
Guidelines For Establishment of Forum For Redressal of Grievances of the Consumers 2010
Renewable Power Purchase obligation, its compliance and REC frame work implementation) Regulations, 2011 March 2011
No.11 JKSERC (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 April 2011
No.12 JKSERC (Terms and Conditions for Determination of Distribution Tariff) Regulations, 2011. April 2011
No.13 JKSERC (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011  (Part-B) April 2011
No.14 JKSERC (Consolidated Amendments) Regulations, 2011 July, 2011
No.15 JKSERC (Supply Code) Regulations, 2011 July, 2011
No.16 JKSERC ( Demand Side Management ) Regulations, 2011 August, 2011
No.17 JKSERC(Open Access in Intra-State Transmission and Distribution) Regulations , 2011 December, 2011
No.18 Commission extends dead line of metering by PDD upto June 2013 26 April, 2012
No.19 J&K SERC (Open Access in Intra-State Transmission and Distribution) 11 July, 2012
No.20 J&K SERC (Consumer Grievance Redressal Forum, Ombudsman and Consumer Advocacy) Regulations, 2012 . 27 August , 2012
No.21 J&K SERC (Multi Year Distribution Tariff) Regulation, 2012.

Part-B Distribution Formats

6 September, 2012
No.22 J&K SERC (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2012.

Part-B Transmission Formats

6 September, 2012
No.23 J&K SERC (Distribution Code) Regulations, 2012 08.10.2012
No.25 J&K SERC (Compliance Audit) Regulations, 2012. 08.10.2012
No.27 Renewable Purchase Obligation (RPO) Target 05.03.2013
NO.28 Jammu and Kashmir State Electricity Regulatory Commission (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2013. 17.05.2013
No.29 J&K SERC (Consolidated Amendments) Regulations, 2013. 02.07.2013
NO.30 J&K SERC (Open  Access in Intra-State Transmission and Distribution) Regulation 02.07.2013
No31 Notification for the fee for filing appeals before the Appellate Authorities 02.07.2013
No.32 Constitution of State Advisory Committee (SAC) 23.10.2013
No.33 Amendment to Annexure-II of J&K SERC (Conduct of Business) Regulations, 2005 11.11.2013
No.34 Nomination as SAC Member Shri Shakeel Qalander 10.12.2013
No.35 JKSERC (Licensing) Regulations, 2013 17.12.2013
No.36 Amendment to Regulation JKSERC/15 dt. 20.07.2011 of J&K SERC Supply Code 2011, in terms of Regulation 7.56 19.12.2013
No.38 JKSERC (charges payable during FY 2014-15 by Open Access Customers) Transmission/Distribution (Wheeling Charges) 10.07.2014
No.39 Partial Modification of the Notification No.:32/JKSERC of 2013 dated 23.10.2013 07.08.2014
No.40 Notification on Designation of State Agency under JKSERC (Renewable Power Purchase Obligation, its Compliance and REC Framework Implementation) Regulations, 2011 05.09.2014
No.41 Transmission/Distribution (Wheeling Charges) for FY 2015-16 14.05.2015
No.43 JKSERC (Terms and Conditions of Intra-State Open Access) Regulations, 2015 10.07.2015
No.44 JKSERC HEREBY REVISES THE   RENEWABLE POWER PURCHASE OBLIGATIONS (RPO) TARGETS FROM FYs 2015-16 & 2016-17 AND SPECIFIES THE RPO FOR FY 2017-18 ONWARDS UPTO FY 2021-22 05.08.2015
No.46 Modification of notification No. 10/J&K/SERC (Consolidated Amendment) Regulations 2008 dated 22-12-2008. 08.10.2015
No.47 JKSERC (Grid Interactive Rooftop Solar Photo Voltaic Systems Based on Net Metering) Regulations, 2015 15.10.2015
NoThe site designed and developed by NIC J&K The contents provided and maintained by JKSERC

(This site can be best viewed in 1024X768 )

NTPC

Coal Based Power Stations

Sr. No. COAL BASED(Owned by NTPC) STATE COMMISSIONED CAPACITY(MW)
1. Singrauli Uttar Pradesh 2,000
2. Korba Chhattisgarh 2,600
3. Ramagundam Telangana 2,600
4. Farakka West Bengal 2,100
5. Vindhyachal Madhya Pradesh 4,760
6. Rihand Uttar Pradesh 3,000
7. Kahalgaon Bihar 2,340
8. Dadri Uttar Pradesh 1,820
9. Talcher Kaniha Orissa 3,000
10. Feroze Gandhi, Unchahar Uttar Pradesh 1,050
11. Talcher Thermal Orissa 460
12. Simhadri Andhra Pradesh 2,000
13. Tanda Uttar Pradesh 440
14. Badarpur Delhi 705
15. Sipat Chhattisgarh 2,980
16. Mauda Maharashta 1,660
17. Barh Bihar 1320
18. Bongiagaon Assam 250
Total 35,085

Coal Based Joint Ventures/Subsidiaries:

Sr. No. COAL BASED(Owned by JVs/Subsidiaries) STATE COMMISSIONED CAPACITY
1. Durgapur West Bengal 120
2 Rourkela Orissa 120
3 Bhilai Chhattisgarh 574
4 Kanti Bihar 610
5 IGSTPP, Jhajjar Haryana 1500
6 Vallur Tamil Nadu 1500
7 Nabinagar-BRBCL Bihar 250
Total 4,674

Gas Based Power Stations

Sr. No. GAS BASED

(Owned by NTPC)

STATE COMMISSIONED
CAPACITY(MW)
1. Anta Rajasthan 419.33
2. Auraiya Uttar Pradesh 663.36
3. Kawas Gujarat 656.20
4. Dadri Uttar Pradesh 829.78
5. Jhanor-Gandhar Gujarat 657.39
6. Rajiv Gandhi CCPP Kayamkulam Kerala 359.58
7. Faridabad Haryana 431.59
Total 4,017.23

Gas Based Joint Ventures/Subsidiaries:

Sr. No. COAL BASED (Owned by JVs/Subsidiaries) STATE COMMISSIONED CAPACITY
1. RGPPL Maharashtra 1967.08
Total 1,967.08

Hydro Based Power Projects

Sr. No. HYDRO BASED STATE APPROVED
CAPACITY(MW)
COMMISSIONED
CAPACITY (MW)
1. Koldam (HEPP) Himachal Pradesh 800 800
2. Tapovan Vishnugad (HEPP) Uttarakhand 520
3. Singrauli CW Discharge(Small Hydro) Uttar Pradesh 8
4. Lata Tapovan Uttrakhand 171
5. Rammam West Bengal 120
Total 1,519 800

Renewable Energy Projects

Sr. No. Project State/UT Capacity (MW)
1. Dadri Solar PV Uttar Pradesh 5
2. Port blair Solar PV Andaman & Nicobar Island 5
3. Ramagundam Solar PV (Phase -I) Telangana 10
4. Talcher Kaniha Solar PV Odisha 10
5. Faridabad Solar PV Haryana 5
6. Unchahar Solar PV Uttar Pradesh 10
7. Rajgarh Solar PV Madhya Pradesh 50
8. Singrauli Solar PV Uttar Pradesh 15
Total 110

NHPC

Project Name State Installed Capacity(MW) Total Capacity(MW) Year Of Commission
Baira Siul Himachal Pradesh 3 * 60 180 1981
Loktak Manipur 3 * 35 105 1983
Salal Jammu & Kashmir 6 * 115 690 1987
Tanakpur Uttarakhand 3 * 40 120 1992
Chamera – I Himachal Pradesh 3 * 180 540 1994
Uri – I Jammu & Kashmir 4 * 120 480 1997
Rangit Sikkim 3 * 20 60 1999
Chamera – II Himachal Pradesh 3 * 100 300 2004
Indira Sagar Madhya Pradesh 8 * 125 1000 2005
Dhauliganga – I Uttarakhand 4 * 70 280 2005-06
Dulhasti Jammu & Kashmir 3 * 130 390 2006-07
Omkareshwar Madhya Pradesh 8 * 65 520 2007
Teesta – V Sikkim 3 * 170 510 2008
Sewa – II Jammu & Kashmir 3 * 40 120 2010
Chamera-III Himachal Pradesh 3 * 77 231 2012
Teesta Low Dam – III West Bangal 4 * 33 132 2013
Nimmo-Bazgo Jammu & Kashmir 3 * 15 45 2013
Chutak Jammu & Kashmir 4 * 11 44 2013
Uri-II Jammu & Kashmir 4 * 60 240 2014
Parbati – III Himachal Pradesh 4 * 130 520 2014
Total 6507 MW